Milestone Dependency
This is the ability to Link Milestones end to end and create a critical path.
- default link will be Finish to Start
- Changing a Milestone Deadline Date changes any downstream linked Milestones the same number of days.
Task Dependency
When a Milestone Kickoff Date and Deadline Date changes, all Tasks for that Milestone should also change.
- Task Dates change if the Milestone Kickoff and Deadline Dates both change and the duration remains the same
- If only one of the Dates changes Tasks will not be affected
Wish List Items:
Sub Milestone and Task Dependency
When a Parent Milestone moves the Sub Milestones and Tasks should also move the same duration amount.