Skip to content
New issue

Have a question about this project? Sign up for a free GitHub account to open an issue and contact its maintainers and the community.

By clicking “Sign up for GitHub”, you agree to our terms of service and privacy statement. We’ll occasionally send you account related emails.

Already on GitHub? Sign in to your account

Sumer Release Progress Tracking #2002

Closed
bedeho opened this issue Jan 11, 2021 · 4 comments
Closed

Sumer Release Progress Tracking #2002

bedeho opened this issue Jan 11, 2021 · 4 comments
Assignees

Comments

@bedeho
Copy link
Member

bedeho commented Jan 11, 2021

This issue will track the weekly progress of the Sumer release, which has the following plan

#2045

Estimation Methodology

Only issues in TODO and In progress stages are counted. ...

@mnaamani
Copy link
Member

Date

26th January 2021

Estimated Remaining Work

Person Hours Weeks
Arsen 12 1
Mokhtar 120 3
Klaudiusz 0 0
Metin 69 2
Dmitrii 189 5
Andy 0 0
Edvin 0 0
Ben 0 0
Ben [tests] 0 0
Martin 112 3
Total 502 14

New Estimated Release Date

March 30th 2021

Detected Overruns & Corrections

This is the first tracking issue, several team members still need to provide their estimates.

Updated Milestones

Production

Person Date
Arsen Feb. 2
Mokhtar Feb 16.
Klaudiusz -
Metin Feb. 9
Dmitrii March 2
Andy -
Edvin -
Ben -
Total March 2

Testing & Fixes

Person Date
Ben [tests] March 2
Martin March 23
Total March 23

Release (1 week buffer)

March 30th

@mnaamani
Copy link
Member

mnaamani commented Feb 2, 2021

Date

1st February 2021

Estimated Remaining Work

Person Hours Weeks Notes
Arsen 12 1 -
Mokhtar 105 3 -
Atlas Team 171 5 (512h / 3 members)
Metin 48 2 -
Dmitrii 153 4 -
Andy 9 1 -
Edvin 0 0 -
Ben 51 2 -
Ben [tests] 24 1 -
Martin 112 3 -
Total 502 14 -

New Estimated Release Date

April 6th 2021

Detected Overruns & Corrections

  • More detailed estimates from Andy and Arsen needed. For more accurate estimate.
  • New estimates for Atlas has pushed the release by additional week. Consider adding one more team member?

Updated Milestones

Production

Person Date
Arsen Feb. 9
Mokhtar Feb 23.
Atlas Team Mar 9
Metin Feb. 16
Dmitrii Mar. 2
Andy Feb. 9
Edvin -
Ben Feb 16.
Total March 9

Testing & Fixes

Person Date
Ben [tests] March 16
Martin March 30
Total March 30

Release (1 week buffer)

April 6th

@mnaamani
Copy link
Member

Quick Update - Mon Feb 15

This is still rough as we need to create tasks for all CLI, Query-Node mappings/input-schemas and integration work.

Screen Shot 2021-02-15 at 10 24 21 AM

@mnaamani
Copy link
Member

mnaamani commented Mar 1, 2021

Date

1st March 2021

Estimated Remaining Work

Person Hours Weeks Notes
Arsen 31 1
Mokhtar 36 1 -
Atlas Team 73 2 (291h / 4 members)
Metin 12 1 -
Dmitrii 0 0 -
Andy 18 1 -
Edvin 0 0 -
Ben 51 2 -
Ben [tests] 24 1 -
Martin 112 3 -
Total 363 12 -

New Estimated Release Date

April 12th 2021

Detected Overruns & Corrections

  • pushed backed by an additional week. ( 2 weeks behind initial estimate )
  • More detailed estimates from Edvin needed for more accurate estimate.
  • Additional developer joined Atlas team - now team size = 4 which so far having a positive impact on progress.
  • Query node we still don't have a fully working implementation in Sumer branch - PR pending test and review

Updated Milestones

Production

Person Date
Arsen Mar. 8
Mokhtar Mar. 8
Atlas Team Mar. 15
Metin Mar. 8
Dmitrii complete
Andy Mar. 8
Edvin n/a
Ben Mar. 15
Total March 15

Testing & Fixes

Person Date
Ben [tests] March 22
Martin April 5
Total April 5

Release (1 week buffer)

April 12th 2021

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
None yet
Projects
None yet
Development

No branches or pull requests

2 participants